Sungun Copper Concentration Plant

Project information

Project name Sungun Copper Concentration Plant

Client National Iranian Copper Industries Company

Contract type EP

Launching year 2006

Location East Azerbaijan – Ahar province

About the project

Goals Establishing a copper concentration plant with the capacity of 7 million tons mine ore as the plant feed and producing 150,000 tons of (about) 30% grade concentrate per year in phase one.

Project details IRITEC as the consultant engineer, has been in charge of design, local equipment procurement, supervision on the construction and installation, foreign equipment inspection and also planning and project control management.

Project measurements are as follows:

– Local equipment: 6000 tons

– Foreign equipments: 3800 tons

– Concreting volume: 82750 m3

– Steel structure weight: 3600 tons

– Number of local manufacturers: 60